Latest launch status update from Kourou

by

– SPIRE LL verified to be latched with DVM measurement on Tuesday,  5th May 2009.
– Herschel cryostat filling level will be maintained inside BAF (ongoing)
– Herschel / Planck Launch Countdown “Dress Rehearsal” successfully completed on Thursday, 7th May 2009 !!!
– HIFI LOU and LOU baffle nitrogen purge will be removed on Saturday, 9th May 2009.
– Fairing integration scheduled for Sunday, 10th May 2009.
– Launcher roll-out to launch pad on Wednesday, 13th May 2009.
– Herschel / Planck Launch on Thursday, 14 May 2009 @13:12:00 (UTC)

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s


%d bloggers like this: